540 A.2d 710
(5507)Appellate Court of Connecticut
DUPONT, C. J., BORDEN and STOUGHTON, Js.
The plaintiff plumbing and heating contractor sought damages from the defendant general contractor for breach of an alleged oral agreement by the defendant to award the plaintiff the mechanical portion of a bank construction contract. After the plaintiff had submitted its bid, which the defendant used in its own bid for the general contract, the defendant entered into a contract with another contractor at a lower price. The trial court rendered judgment on the jury verdict in favor of the defendant, and the plaintiff appealed challenging the trial court’s instructions to the jury. Held that because the plaintiff’s theory of the case was that the defendant had accepted its bid, conditioned only on the defendant’s being awarded the contract by the bank, the trial court erred in instructing the jury that before it could find that the plaintiffs bid was accepted and a contract formed, it first had to conclude that the plaintiff had submitted the lowest bid; accordingly, the judgment was set aside and the case was remanded for a new trial.
Argued February 11, 1988
Decision released April 26, 1988
Action to recover damages for breach of an oral agreement to accept the plaintiff’s construction bid, brought to the Superior Court in the judicial district of Litchfield and tried to the jury before Pickett, J.; verdict and judgment for the defendant, from which the plaintiff appealed to this court. Error; further proceedings.
Zbigniew S. Rozbicki, for the appellant (plaintiff).
Charles F. Brower, with whom was Jeffrey C. Nicholas, for the appellee (defendant).
BORDEN, J.
The plaintiff, a plumbing and heating contractor, brought this action against the defendant, a general contractor, for breach of an alleged conditional oral agreement by the defendant to award the plaintiff the mechanical portion of a construction project. The plaintiff appeals from the judgment rendered in
Page 262
favor of the defendant, after a jury trial, claiming that the trial court erred (1) in its instructions to the jury, and (2) in denying the plaintiff’s motion to poll the jury after the verdict was announced. We find error.
The plaintiff’s theory of recovery, as alleged in its complaint and supported by the evidence, was that the defendant contacted the plaintiff to solicit a bid for plumbing, heating and air conditioning work as a subcontractor on a proposed addition to the Salisbury Bank (bank). The bid was solicited by the defendant in conjunction with its proposed bid to the bank to perform the project as a general contractor. The defendant’s bid had to be submitted to the bank by 2 p.m. on September 1, 1983. The plaintiff claimed that the defendant represented that, in order to meet the defendant’s bid submission deadline, the plaintiff had to submit its bid to the defendant by 12 noon on that day so that the defendant could timely submit its bid.
At 11:43 p.m. on September 1, the plaintiff submitted a bid to the defendant. The plaintiff claimed that the defendant’s agent represented to the plaintiff that its bid was the lowest, that the plaintiff would be designated as a subcontractor in the bid to the bank, and further that if the defendant was awarded the general contract, the plaintiff would be awarded the plumbing, heating and air conditioning subcontract. The defendant used the plaintiff’s bid in the bid to the bank. The defendant was awarded the general contract but refused to award the plaintiff the subcontract.
The defendant claimed that no acceptance of the plaintiff’s bid ever took place, and that any representations made by the defendant to the plaintiff regarding whether the plaintiff would be used on the project depended on whether the plaintiff’s bid turned out to be the lowest. Before 2 p.m. on September 1, and while the defendant’s president was en route to the
Page 263
bank to submit the defendant’s bid on the project, the defendant received a lower bid from another subcontractor. After the defendant’s bid was accepted by the bank, the defendant employed that other subcontractor to do the mechanical portion of the project, and executed a formal written contract with that subcontractor after approval of the subcontractor by the owner and architect.
The plaintiff first claims that the court erred by charging the jury that, before it could find that the plaintiff’s bid was accepted by the defendant and a contract formed, the jury first had to conclude that the plaintiff submitted the lowest bid before the time that the defendant delivered its bid to the bank.[1] We agree.[2]
Page 264
The court erred by instructing the jury that it must first find that the plaintiff’s bid was the lowest at the time the defendant submitted its bid on the project to the bank. This fact, however, was not relevant to the plaintiff’s theory of the case. The plaintiff’s case was based upon proof that the defendant accepted the plaintiff’s bid orally on September 1 and created a contract by indicating to the plaintiff that, if the defendant was awarded the contract on the project, the defendant would use the plaintiff as a subcontractor. The plaintiff’s legal claim was that its bid constituted an offer to which the defendant’s agent manifested an acceptance subject only to the condition precedent that the defendant be chosen as the general contractor on the project. See generally J. Calamari J. Perillo, Contracts (3d Ed.) 11-1, 11-2, 11-5.
Page 265
“A condition precedent is a fact or event which the parties intend must exist or take place before there is a right to performance. A condition is distinguished from a promise in that it creates no right or duty in and of itself but is merely a limiting or modifying factor. If the condition is not fulfilled, the right to enforce the contract does not come into existence. Whether a provision in a contract is a condition the nonfulfillment of which excuses performance depends upon the intent of the parties, to be ascertained from a fair and reasonable construction of the language used in the light of all the surrounding circumstances when they executed the contract.” (Citations omitted.) Lach v. Cahill, 138 Conn. 418, 421, 85 A.2d 481 (1951). The issue of whether or not the plaintiff’s bid was the lowest simply was not an issue in this case. Instead, whether the plaintiff’s bid was accepted by the defendant as alleged was the central factual and legal dispute for the jury to determine.[3] The challenged instruction, therefore,
Page 266
had the effect of charging the plaintiff’s theory of recovery out of the case and, under the circumstances, was tantamount to improperly directing a verdict in the defendant’s favor.[4]
There is error, the judgment is set aside and the case is remanded for a new trial.
In this opinion the other judges concurred.
(1976); Mihalek v. Cichowski, 4 Conn. App. 484, 486, 495 A.2d 721 (1985); and since the plaintiff raised his claims of error to the extent permitted and desired by the trial court and sufficiently to apprise the trial court of the claim which he now presses on appeal, we conclude that, under these circumstances, counsel complied with the requirements of Practice Book 315 to “state distinctly the matter objected to and the ground of objection.” The decision in Smith v. Czescel, 12 Conn. App. 558, 562 n. 2, 533 A.2d 223 (1987), is distinguishable from this case. In Smith, the truncated exception failed to apprise the trial court adequately of the claim later urged on appeal, and, in Smith, the plaintiff’s counsel did not attempt to protect the record further for appeal after first being cut short by the trial court. Here, by contrast, the plaintiff’s counsel was persistent, and did make as adequate an exception as was possible under the circumstances.
Page 267